The Schedule

How dates are calculated, and whose delay is whose.

Calculated from promises

Each piece of work starts when its inputs are verified and takes its owner's working time. If an input arrives late, the work's due date moves by the same number of days. The Schedule tab shows one project's work as bars, from the project you last opened.

vectorxpro.com/project/app
The Schedule: one project's work as bars, grouped by phase, calculated from the owners' promises

Inherited or owned

Days late because an input was late are inherited: not the owner's delay. Days late on the owner's own work are owned. Pushed by upstream shows inherited days; Late shows owned ones. A link whose work will arrive after its Date A is a date conflict.